To Meeting Agendas & Minutes - Current Action Items - Back to Projects Board Overview
Table of Contents
1.1 Software Assessment
1.1 Software Assessment
Building Software Assessment Team
2009-12-24
{0}
Arbitrated Background Check Alexander Prinsier
{-} init
no CM, no A avail, face-2-face meeting schedules failed
Arbitrated Background Check Markus Warg; appointed to Software Assessment
2010-02-26
Build up test maschine by critical sysadmin team
done
Documentation Build up test maschine by critical sysadmin team
done
Recovery Process to Build up test maschine from Documentation
{+}
Setup a repository (SVN)
done
repository test SVN
failed
{-}
Setup a repository (GIT)
done
repository test GIT, ongoing tests
success
Setup a Testserver
done / at ...
Deploy a Testserver Mgmt Environment
2010-04-15
2010-08-18
Testing Testserver and Testserver Mgmt Environment
2010-08-04
2010-09-21
{+}
Test with first software patch
2010-09-21
2010-09-27
{+}
Build transfer Package from software patch
2010-09-25
2010-10-07
{+}
Build and document the transfer process of Software patches
2010-10-27
{0}
...
Dependent
on 1.1 are
1.4
2.1
3.1
Notes
- m20091220.2 - 2009-12-24 - Request to propose new Software Assessment team members
- That, the board is of the opinion that more software assessment members are needed, and, requests the Software Assessment Team Leader to propose new members (Dirk Astrath, Markus Warg, Bernhard Froehlich and Alexander Prinsier) for addition to the Software Assessment Team, and asks that ABCs be requested as soon as possible.
- Philipp G 2010-01-16
- have been asked (m20091220.2) to propose new team members for the Software Assessment team. I talked to the suggested candidates, roughly evaluated their qualifications and time-budgets, and came to the conclusion that we should start the process with Alexander Prinsier and Markus Warg. Therefore please start the arbitrated Background Checks on Alexander Prinsier and Markus Warg now.
Status
- Transfer process needs to be deployed and documented.
- Proposals: Process of Software Assessment
1.2 Software Development
1.2 Software Development
Building Software Development Team
...
...
...
Status
- Not started / Developers team not yet build ... ?
1.3 Software Test Team
1.3 Software Test Team
Building Software Test Team
2010-08-04
2010-08-18
{+}
Status
- Building Test Team: finished
1.4 Change Point Count System
1.4 Change Point Count System (Thawte Patch) - Deadline Nov 16th 2010x1
Change the points count system
{0}
1.1
Updates for critical system
written
Testing to the critical system
2010-10-08
{0}
Move to the critical system
{-}
Status
depends on 1.1 software assessment project
- * depends on software updates to the critical system - which ones ??
x1) Deadline relates to the end of Thawte Points transfer program as of removal of the 150 points received by the Points transfer. Each transfered Member/Assurer needs to do re-assurances receiving Assurance points and also by doing Assurances to receive experience points. This needs to be communicated to the community.
1.5 New Software - BirdShack
1.5 New Software - BirdShack
New development of the critical system
Notes
- During CeBIT 2009 discussions between PD, Ian and Mario discovered that the current CAcert software (libressl) might be hard to maintain.
- For doing more investigation on this, these three plus Alejandro met up in Innsbruck for a week for digging into it.
- Analysing the current software revealed that the software had grown by time and is not well designed and possibly would not stand an audit.
Status
- stagnent
re new software
- Which other project is related to "new software" beside 1.5?